Office quality management system manual and policy

BBM-STD-96 · V0.2 · This manual describes how BABOOM plans, delivers, checks and improves its services so that every proposal, design, specification, submission and site decision meets the...

Download WordAll standards

BBM-STD-96-QUALITY_MANAGEMENT_SYSTEM-V0.2 | Office standard | 5 November 2026 | V0.2 | Private controlled WIP draft for office review

VersionDateChange
V0.12026-11-04First issue: the office quality management system (QMS) for the whole practice, not only BIM. Aligned to ISO 9001:2026 (published 16 Sep 2026). Adds proposals, contract review, design review per discipline, specifications, sustainability ratings, authority submissions, site supervision, document control, client feedback, internal audit and management review to the BIM quality plan of BBM-STD-68. Procedures in BBM-STD-97; objectives and KPIs in BBM-STD-98.
V0.22026-11-05Standard watch no. 1: ISO 19011:2026 (edition 4; the 2018 edition is withdrawn) cited in §9.2, §11 and the references

1 Purpose scope and status#

This manual describes how BABOOM plans, delivers, checks and improves its services so that every proposal, design, specification, submission and site decision meets the client's requirements, the law and the office's own standard. It covers the whole practice: architecture (ARC), interiors (INT), landscape (LSC), structure (STR), mechanical, electrical and plumbing (MEC, ELE, PLU), fire and life safety (FLS) and any other appointed discipline (codes per BBM-STD-93), in the Dubai and Abu Dhabi offices, from enquiry to closeout and aftercare.

The QMS is aligned with ISO 9001:2026, edition 6, published 16 September 2026 (register row ED-ISO9001 in BBM-STD-51 §3). No certification is claimed by this document. Certification transition, where the office holds or seeks a certificate: Global ACI (which took over the IAF role on 1 January 2026) set a three-year transition; ISO 9001:2015 certificates stop being valid after 30 September 2029, and from 31 March 2028 new accredited certifications are issued only to the 2026 edition. The QMS owner confirms the transition audit date with the certification body and records it in the management review.

The QMS has three documents and one set of checklists:

DocumentHolds
BBM-STD-96 (this manual; QMS numbering)Policy, context, scope, process map, roles and RACI, how each ISO 9001:2026 clause is met
BBM-STD-97 Quality proceduresQP-01 to QP-15: purpose, scope, roles, steps, records, checklist ID and references for each office process
BBM-STD-98 Quality KPIsQuality objectives as measurable KPIs with formula, target, frequency and owner
Checklists in 07-QA-QCOne workbook per area (01-BIM to 09-AUDIT), same columns as the BIM checklist

The BIM and information quality plan stays in BBM-STD-68 and Manual V0.5 §9, with its checklist 07-QA-QC\01-BIM\BBM-STD-68-CHECKLIST-V1.0.xlsx. This manual does not repeat it; it places it inside the office QMS as the information-quality sub-system.

2 Quality policy#

Approved by the practice director; displayed in both offices and on the standards front page; reviewed at each management review.

BABOOM designs and supervises buildings that are safe, lawful, buildable and fit for their users. We do this by:

  1. understanding and recording what each client and authority requires before we commit, and declining work we cannot do well;
  2. checking every output by a competent person who did not produce it, before it leaves the office;
  3. coordinating all disciplines into one consistent design, specification and model;
  4. meeting the green-building, fire and building codes of the plot as a minimum, and the client's sustainability targets;
  5. recording our decisions and evidence so they can be traced for the life of the building;
  6. promoting a quality culture and ethical behaviour: we report errors early, fix their causes and share the lessons;
  7. measuring our performance against the objectives in BBM-STD-98 and improving the system every quarter.

3 Context scope and process map#

Context (ISO 9001:2026 4.1, 4.2). The QMS owner keeps one context register, reviewed at least yearly and at each management review: internal issues (staff capacity, software and CDE, maturity of office standards), external issues (UAE building, fire and green-building law, authority portals and BIM permit circulars, market and fee pressure, climate change and heat, decennial liability under UAE Civil Transactions Law (register ED-UAE-CTL in BBM-STD-51 §3: Art. 821 of Federal Decree-Law 25 of 2025; Art. 880 of Federal Law 5/1985 for contracts signed before 1 June 2026)), and interested parties with their requirements (clients, authorities DM/DMT/DDA/Civil Defence, master developers, contractors, subconsultants, staff, insurers, building users). Climate change is considered as an issue (the 2024 amendment is part of the 2026 text).

Scope (4.3). "Architectural, interior, landscape, structural, MEP and fire and life safety design consultancy, specification, authority approvals, sustainability rating support and construction supervision for building projects in the UAE." No ISO 9001 requirement is excluded; clause 7.1.5 (monitoring and measuring resources) applies to survey and test equipment the office owns or relies on.

Project folders follow the one project folder tree of Manual V0.5 §12.1; this manual defines no folders.

Process map (4.4). One owner and one procedure per process. Management processes steer, core processes deliver, support processes enable.

TypeProcessProcedureOwner (function)Checklist (07-QA-QC)
ManagementPolicy, objectives, risk and opportunity, changeBBM-STD-96 §5-6Practice director09-AUDIT
ManagementInternal auditQP-13QA/QC lead09-AUDIT (Internal audit)
ManagementManagement reviewQP-14Practice director09-AUDIT (Management review)
ManagementNonconformity, corrective action, lessons learnedQP-11QA/QC lead09-AUDIT (NC and lessons)
CoreProposals, go/no-go and contract reviewQP-01Practice director03-PROPOSALS
CoreProject quality planQP-02Project director09-AUDIT (Project quality plan)
CoreDesign review and verification per disciplineQP-03Discipline leads02-DESIGN-REVIEW
CoreInterdisciplinary coordination and constructabilityQP-04Lead design consultant02-DESIGN-REVIEW
CoreSpecificationsQP-05Specification lead04-SPECIFICATIONS
CoreSustainability ratingsQP-06Sustainability lead / PQP05-SUSTAINABILITY
CoreAuthority submissionsQP-07Authority liaison06-SUBMISSIONS
CoreDrawing and model issueQP-08 (BBM-STD-68)Information manager01-BIM
CoreSite supervision and inspectionsQP-09Supervising engineer07-SUPERVISION
CoreClient feedback and complaintsQP-12Practice director09-AUDIT (Client feedback)
SupportDocument control and recordsQP-10Document controller08-DOCUMENT-CONTROL
SupportSubconsultants and suppliersQP-15Practice director03-PROPOSALS (Subconsultants)
SupportCompetence and trainingBBM-STD-82BIM Manager with the practice director09-AUDIT (7.2)
SupportStandards, templates and librariesBBM-STD-51, BBM-STD-65BIM Manager01-BIM
SupportIT, CDE, security and recordsBBM-STD-76, BBM-STD-87, BBM-STD-90CDE/IT and Security leads08-DOCUMENT-CONTROL

Project flow: enquiry, QP-01, appointment, QP-02 quality plan; each RIBA stage 0-7 runs QP-03/04/05/06 and issues through QP-08 and QP-10; QP-07 submissions at the authority gates; QP-09 on site; closeout with QP-11 lessons and QP-12 feedback. Gate families and outcomes follow BBM-STD-93 §5-6.

4 Roles responsibilities and authorities#

Office functions are those of BBM-STD-55 §2; named holders live in the private Directory. This section adds the QMS duties. The practice director owns the office QMS; the BIM Manager's quality framework is its information part. A role label grants no contractual or statutory authority; the consultant of record signs authority submissions within its registration.

FunctionQMS duty
Practice director (top management)Owns the QMS and the policy; sets objectives; chairs management review; decides go/no-go and signs appointments; provides resources; promotes quality culture and ethical behaviour (5.1.1 i))
QA/QC lead (QMS coordinator)Maintains BBM-STD-96/97/98 and the checklists; runs the audit programme; keeps the NC, CAR and lessons logs; reports KPIs; independent of the work audited
BIM ManagerOwns the information-quality framework (BBM-STD-68, Manual §9), standards register, templates, libraries and training records
Project directorAccountable for project quality: approves the project quality plan, issues and stage gate outcomes
Project manager / lead design consultantRuns the quality plan, coordination (QP-04), programme, change and client communication
Discipline leads (ARC, INT, LSC, STR, MEP, FLS)Design verification, independent checking in the discipline (L1), competence of authors and checkers, approval to share
Specification leadSpecification set-up, coordination and issue (QP-05)
Sustainability lead / PQPRating applicability, targets, evidence and submissions (QP-06)
Authority liaison and consultant of recordJurisdiction test, submission packages, comment responses, approvals (QP-07, BBM-STD-85)
Supervising / resident engineerSupervision plan, submittals, inspections, NCRs, RFIs, completion approvals (QP-09)
Document controllerRegisters, transmittals, incoming information, records and closeout (QP-10)
Information managerNaming, CDE states, container checks and release (QP-08, BBM-STD-68)
All staffFollow the procedures; report errors, near misses and complaints; contribute lessons

4.1 QMS RACI#

R performs, A is the single accountable function, C is consulted, I is informed (BBM-STD-55 §3 rules: one A per row).

ActivityPractice directorQA/QC leadBIM ManagerProject directorPM / lead designerDiscipline leadDoc controllerSupervising engineer
Quality policy and objectivesA/RRCCIIII
Go/no-go and contract review (QP-01)AIIRCCIC
Project quality plan (QP-02)ICCARCCC
Design review per discipline (QP-03)ICIACRII
Coordination and constructability (QP-04)ICCARRIC
Specification (QP-05)ICIACRIC
Sustainability rating (QP-06)ICCARRIC
Authority submission (QP-07)IICARCCI
Drawing and model issue (QP-08)ICACRRRI
Site supervision (QP-09)ICIACCIR
Document control (QP-10)ICCACIRI
Nonconformity and CAPA (QP-11)IA/RCCRRIR
Client feedback (QP-12)ARIRCIII
Internal audit (QP-13)IA/RCCCCCC
Management review (QP-14)A/RRCCIIII
Subconsultant control (QP-15)ACIRRCII

5 Leadership#

The practice director demonstrates leadership by: holding the QMS accountable for results; aligning policy and objectives with the office strategy; building QMS steps into the normal project workflow (the checklists are the working tools, not extra forms); providing people, software and time; communicating why quality matters; promoting improvement; and promoting a quality culture and ethical behaviour (ISO 9001:2026 5.1.1 i)). Evidence kept: management review minutes, policy communications, decisions to decline unsuitable work (go/no-go) and no-blame reporting of errors (QP-11). Ethics: conflicts of interest are declared at go/no-go; no gift that could influence a decision; no certification or rating claim that is not current.

Customer focus (5.1.2): client and statutory requirements are recorded at QP-01 and in the Basis of Design (BBM-STD-12); client satisfaction is measured (BBM-STD-98 K-CL).

6 Planning#

Risks and opportunities (6.1.1-6.1.3). One office register with two separate lists: risks with actions to address them (6.1.2) and opportunities with actions to pursue them (6.1.3). Likelihood x impact on the Manual 1-5 scale; 15-25 escalates to the practice director. Project risks start in the bid risk register (QP-01) and pass to the project quality plan (QP-02). Typical office risks: unclear scope, authority rejection, design error reaching site, subconsultant failure, staff overload, data loss. Typical opportunities: repeat clients, BIM permit capability, green-rating expertise, the reusable details library.

Quality objectives (6.2). The objectives are the KPIs of BBM-STD-98, each measurable, owned and reviewed quarterly.

Planning of changes (6.3). A change to the QMS (new procedure, checklist revision, standard change) records its purpose and consequences, effect on the QMS, resources, responsibilities, how its effectiveness will be monitored and evaluated, how it is communicated and how its results will be reviewed (6.3 e)-g)). Changes go through the BBM-STD-51 register with a ChangeID; pilot on one project before office-wide use where the risk warrants it.

7 Support#

ClauseHow it is met
7.1 Resources, infrastructure, environmentCapacity checked at go/no-go and in the project quality plan; software releases per BBM-STD-91; CDE per BEP; backup and recovery per BBM-STD-76
7.1.5 Monitoring and measuring resourcesSurvey instruments and site test equipment (own or contractor's) checked for valid calibration before results are accepted (QP-09)
7.1.6 Organisational knowledgeOffice standards, the details and family libraries, the lessons log (QP-11) and the training records; reviewed at management review
7.2 CompetenceRole competence and checker authorisation per BBM-STD-82; authority qualification of engineers per the emirate rules (Dubai: DM Administrative Resolution 253 of 2021)
7.3 AwarenessInduction and yearly refresh cover the policy, objectives, each person's contribution, the effect of not following the QMS, and the office quality culture and ethical behaviour (7.3 e))
7.4 CommunicationInternal: coordination meetings, the standards front page, QMS notices. External: transmittals and correspondence per QP-10
7.5 Documented informationOffice standards controlled through BBM-STD-51; project records through QP-10; retention per BBM-STD-76/90 (office minimum 13 years after handover: decennial liability plus claim period)

8 Operation#

ClauseProcedure
8.1 Operational planning and controlQP-02 project quality plan (ISO 10005 structure), linked to the BEP and MIDP/TIDP
8.2 Requirements for services and their reviewQP-01 go/no-go, scope and contract review; changes to requirements through QP-02 change control
8.3 Design and developmentQP-03 design review and verification, QP-04 coordination and constructability, QP-05 specifications, QP-06 sustainability; validation = client acceptance at stage gates and authority approval
8.4 Externally provided processesQP-15 subconsultants and suppliers; supplier-origin model content per BBM-STD-68 §1
8.5 Service provisionQP-07 authority submissions, QP-08 issue, QP-09 supervision; client property (surveys, reports, data) per QP-10; preservation of records per BBM-STD-76
8.6 ReleaseNothing is issued, submitted or certified until its checklist shows no mandatory Fail and the approver signs (QP-08, QP-07, QP-09)
8.7 Nonconforming outputsQP-11; NC-1/2/3 classes per Manual §9.3

9 Performance evaluation#

  • 9.1 Monitoring and measurement: the KPIs of BBM-STD-98, computed monthly or quarterly by the QA/QC lead from the checklists and registers. 9.1.2 client satisfaction: QP-12.
  • 9.2 Internal audit: QP-13; every process audited at least once a year; each audit has stated objectives, scope, criteria and an auditor independent of the area (ISO 19011:2026).
  • 9.3 Management review: QP-14; quarterly and at material incident (the cadence already set for BBM-STD-68), with all 9.3.2 inputs including changes in interested parties' needs (9.3.2 c)).

10 Improvement#

Nonconformities and corrective actions per QP-11; continual improvement through lessons learned, KPI trends, audit findings and client feedback, decided at management review and carried out as controlled changes (§6). Quality culture: errors are reported without blame; the person who finds a systemic issue is credited in the lessons log.

11 ISO 9001:2026 clause map and what changed from 2015#

ISO 9001:2026 clauseWhere in the office QMSChanged from 2015
4.1-4.4 Context, interested parties, scope, processes§3Climate change consideration integrated (from Amd 1:2024)
5.1 Leadership and commitment§5New 5.1.1 i): promote quality culture and ethical behaviour
5.2 Quality policy§2Quality policy added as a quality-specific term
5.3 Roles, responsibilities, authorities§4, §4.1none
6.1 Risks and opportunities§6Split into 6.1.1 determining, 6.1.2 actions to address risk, 6.1.3 actions to address opportunities
6.2 Quality objectives§6, BBM-STD-98Quality objectives added as a quality-specific term
6.3 Planning of changes§6Adds effectiveness monitoring, communication and review of results (6.3 e)-g))
7.1-7.5 Support§77.3 e) awareness of quality culture and ethical behaviour; organisational knowledge made more precise
8.1-8.7 Operation§8, BBM-STD-97Clarified wording
9.1 Monitoring, measurement, analysis§9, BBM-STD-98none
9.2 Internal audit§9, QP-13Objectives required for every internal audit
9.3 Management review§9, QP-149.3.2 "shall include"; new input c) changes in interested parties' needs
10.1-10.3 Improvement§10, QP-11Annex B correspondence table replaced by an expanded Annex A on the intent of clauses 4-10

Clause wording is summarised from the public ISO catalogue, ISO/TC 176 and the Global ACI transition document; confirm against the licensed text before any certification audit. Editions are held once in the BBM-STD-51 §3 register: ED-ISO9001, ED-ISO10005, ED-ISO10006, ED-ISO19011 (ISO 19011:2026, edition 4), ED-ISO10002, ED-LEED (version per project registration) and ED-ADC9-2026.

References#

  • ISO 9001:2026 Quality management systems, Requirements, edition 6, published 16 Sep 2026: https://www.iso.org/standard/9001, checked 2026-11-04.
  • ISO/TC 176 release note and transition dates (23 Sep 2026): https://committee.iso.org/sites/tc176/home/news/content-left-area/news-and-updates/news.html, checked 2026-11-04.
  • Global ACI TECH-3-TR, Transition requirements for ISO 9001:2026 (summary of key changes §3): https://sys.global-aci.org/uploads/documents/TECH-3-TR_2029-09-30_(M)_ISO_9001_2026_Transition_v1_12.pdf, checked 2026-11-04.
  • ISO 10005:2018 quality plans; ISO 10006:2017 quality management in projects (confirmed 2023): https://www.iso.org/standard/70376.html, checked 2026-11-04. ISO 19011:2026 auditing management systems, edition 4 (the 2018 edition was withdrawn on 27 May 2026): https://www.iso.org/standard/19011, checked 2026-11-05; ISO 10002:2018 complaints handling.
  • FIDIC Quality Management briefing note (June 2019) and Organisational and Project Quality report: https://fidic.org/policy/quality, checked 2026-11-04. FIDIC Guide to the interpretation and application of ISO 9001:2015 for the consulting engineering industry (2017).
  • RIBA Plan of Work 2020 Overview: https://www.riba.org/work/insights-and-resources/riba-plan-of-work; RIBA Stage 1 checklist (establish project quality management procedures; RIBA Quality Management Toolkit for Chartered Practices): https://www.riba.org/media/w3epmqnb/1-preparation-and-brief-checklist-pdf.pdf, checked 2026-11-04.
  • UAE Civil Transactions Law Art. 880 decennial liability (overview): https://www.dentons.com/en/insights/articles/2022/may/9/-/media/9cc89da85a674694bbb9ec4b74f35133.ashx, checked 2026-11-04. Not legal advice.
  • Office: BBM-STD-01 Manual §9, BBM-STD-12, 51, 55, 68, 76, 82, 85, 87, 90, 93, 97, 98.